IMPORTANT UPDATES! Mariner's Boathouse Monthly Update: September 2016

posted Oct 3, 2016, 3:23 PM by Greg Papuga   [ updated Oct 3, 2016, 3:23 PM ]

Units 301,302,303,304 are completed for the renovation. We are in the process of completing deep cleans and punch list items on this floor. The 2nd and 1st floors on the south side are due to be completed in the next 2 weeks.

The renovation project met a major delay as all of the cast iron pipes for the plumbing had to be replaced. They were almost completely blocked and corroding in many areas. This was not an issue discovered while doing the model unit last year. It was found when renovating the plumbing in 102 and other south end units. This put the completion date for the project behind. Although it was an unforeseen issue, we are grateful owners can enjoy a very necessary plumbing upgrade!

The north end units will not be started on until we are able to occupy the 3rd floor on the south side. Then, 3 units at a time will be done in a “plumbing stack” replacement sequence, (08, 07, 06, 05 units). With the delay of units being completed, the resort is re-routing incoming exchange and rental guests first, as we will not be able to accommodate them. As the project unfolds, it may be necessary to inform owners that we can no longer accommodate them this year. This is the last and least desirable option. We will make every effort possible to avoid this.

Unit 304

Comments