- The special assessment meeting was held on 8/17. There were many owners
present and they provided excellent input. The final plan is to divide the $675
amount into 3 payments; each $225 per year. This amount will be billed in
November and due March 15th for the next 3 years.
in November and due January 1, 2016.
- The yearly maintenance fee will increase by $13.51 this year. Billing will be sent
- 101 will begin renovations in September and be completed by 10/02/15.
- In 2016 the renovations will begin on the south side of the building week 34. This
side of the building will be completed first followed by the north-side of the
building second. The entire project is scheduled to be completed during week 44.
Pictures of 101 will be posted to our website and Facebook page
after completion. |