  1. The special assessment meeting was held on 8/17. There were many owners present and they provided excellent input. The final plan is to divide the $675 amount into 3 payments; each $225 per year. This amount will be billed in November and due March 15th for the next 3 years. in November and due January 1, 2016.
  2. The yearly maintenance fee will increase by $13.51 this year. Billing will be sent
  3. 101 will begin renovations in September and be completed by 10/02/15.
  4. In 2016 the renovations will begin on the south side of the building week 34. This side of the building will be completed first followed by the north-side of the building second. The entire project is scheduled to be completed during week 44.